Processed Extensions

Processed Extensions

<< Click to Display Table of Contents >>

Navigation:  Latest Release: October 2020 > Changes for Applicants  >

Validity Period and Works Days Extensions

The details of all previously processed extensions made to the validity period and/or works days are shown on the Works Programme.

The information shown is as follows:

The current validity period date and works days

The planned validity period date and works days

 

For each request/extension granted, the following information will be shown:

Request Date

Requested by - if the extension was granted without a request this will display N/A

Extension Type: (Site Works) Days Extension, (Validity Period) Duration Extension

Status: Approved or Denied

Approved End Date - if this was a Works Days extension or the validity period extension request was denied the value shown will be N/A

Approved Works Days - if this was a Validity Period extension or the works days extension request was denied the value shown will be N/A