Processed Extensions |
<< Click to Display Table of Contents >>
Navigation: Latest Release: October 2020 > Changes for Applicants >
The details of all previously processed extensions made to the validity period and/or works days are shown on the Works Programme.
The information shown is as follows:
•The current validity period date and works days
•The planned validity period date and works days
For each request/extension granted, the following information will be shown:
•Request Date
•Requested by - if the extension was granted without a request this will display N/A
•Extension Type: (Site Works) Days Extension, (Validity Period) Duration Extension
•Status: Approved or Denied
•Approved End Date - if this was a Works Days extension or the validity period extension request was denied the value shown will be N/A
•Approved Works Days - if this was a Validity Period extension or the works days extension request was denied the value shown will be N/A